Substation Scout

Werner West - Rocky Run substation interconnection queue

0 active projects totaling 0 MW in the MISO queue, plus 6 with terminal status (shown grayed).

6 MISO queue filings name Werner West - Rocky Run as the point of interconnection, all in Portage County, WI.

0active projects
0active MW
6total filed
Queue IDProjectkVMWResourceStatus
J2366 Not reported 345 160 Solar Withdrawn
J1938 Not reported 345 150 Solar Withdrawn
J1945 Not reported 345 150 Solar Withdrawn
J2365 Not reported 345 115 Battery Withdrawn
J1936 Not reported 345 75 Battery Withdrawn
J1937 Not reported 345 75 Battery Withdrawn

A request with terminal status left the queue as filed. That is a record of the filing, not evidence of injection capacity at this location. Confirm deliverability with MISO before relying on these figures.

Site Scanner

Before you spend weeks on a site, spend seconds screening it.

Scan a site →

Or read a sample report first