Substation Scout

Webster-Lehigh substation interconnection queue

1 active project totaling 300 MW in the MISO queue, plus 1 with terminal status (shown grayed).

2 MISO queue filings name Webster-Lehigh as the point of interconnection, all in Webster County, IA.

1active projects
300active MW
2total filed
Queue IDProjectkVMWResourceStatus
J2436 Not reported 345 300 Wind Active
J2323 Not reported 345 145 Wind Withdrawn

A request with terminal status left the queue as filed. That is a record of the filing, not evidence of injection capacity at this location. Confirm deliverability with MISO before relying on these figures.

Site Scanner

Before you spend weeks on a site, spend seconds screening it.

Scan a site →

Or read a sample report first