Substation Scout

Watseka - Goodland substation interconnection queue

1 active project totaling 150 MW in the MISO queue, plus 3 with terminal status (shown grayed).

1active projects
150active MW
4total filed
Queue IDProjectkVMWResourceStatus
G931 Not reported 138 150 Wind Operational
G537 Not reported 138 100 Wind Withdrawn
G888 Not reported 138 50 Wind Withdrawn
G887 Not reported 138 20 Wind Withdrawn

A request with terminal status left the queue as filed. That is a record of the filing, not evidence of injection capacity at this location. Confirm deliverability with MISO before relying on these figures.