Warrenton Substation substation interconnection queue

2 active projects totaling 339 MW in the MISO queue, plus 1 with terminal status (shown grayed).

3 MISO queue filings name Warrenton Substation as the point of interconnection, all in Warren County, MO.

2active projects
339active MW
3total filed
Queue IDProjectkVMWResourceStatus
J2806 Not reported 161 200 Solar Active
J817 Not reported 161 139 Solar Operational
J2584 Not reported 161 100 Battery Withdrawn

A request with terminal status left the queue as filed. That is a record of the filing, not evidence of injection capacity at this location. Confirm deliverability with MISO before relying on these figures.