1 active project totaling 125 MW in the MISO queue, plus 1 with terminal status (shown grayed).

2 MISO queue filings name Tuscola-Arrowhead Transmission Line as the point of interconnection, all in MI.

1active projects
125active MW
2total filed
Queue IDProjectkVMWResourceStatus
J1920 Not reported 120 125 Solar Withdrawn
J2490 Not reported 120 125 Solar Active

A request with terminal status left the queue as filed. That is a record of the filing, not evidence of injection capacity at this location. Confirm deliverability with MISO before relying on these figures.