Substation Scout

Square Butte Substation East substation interconnection queue

3 active projects totaling 450 MW in the MISO queue, plus 1 with terminal status (shown grayed).

4 MISO queue filings name Square Butte Substation East as the point of interconnection, all in ND.

3active projects
450active MW
4total filed
Queue IDProjectkVMWResourceStatus
J2080 Not reported 230 200 Wind Active
J1888 Not reported 230 175 Wind Withdrawn
J2502 Not reported 230 150 Wind Active
J3070 Not reported 230 100 Wind Active

A request with terminal status left the queue as filed. That is a record of the filing, not evidence of injection capacity at this location. Confirm deliverability with MISO before relying on these figures.