Substation Scout

Silver River substation interconnection queue

1 active project totaling 1.8 MW in the MISO queue, plus 1 with terminal status (shown grayed).

2 MISO queue filings name Silver River as the point of interconnection, all in Baraga County, MI.

1active projects
1.8active MW
2total filed
Queue IDProjectkVMWResourceStatus
J711 Not reported 138 130 Wind Withdrawn
J3800 Not reported n/r 1.8 Gas Active

A request with terminal status left the queue as filed. That is a record of the filing, not evidence of injection capacity at this location. Confirm deliverability with MISO before relying on these figures.