SHERBURNE CO substation interconnection queue

3 active projects totaling 900 MW in the MISO queue.

3 MISO queue filings name SHERBURNE CO as the point of interconnection, all in MN.

3active projects
900active MW
3total filed
Queue IDProjectkVMWResourceStatus
J4194 Not reported n/r 500 Battery Active
J1605 Not reported n/r 200 Solar Active
J4193 Not reported n/r 200 Wind Active

A request with terminal status left the queue as filed. That is a record of the filing, not evidence of injection capacity at this location. Confirm deliverability with MISO before relying on these figures.

Site Scanner

Before you spend weeks on a site, spend seconds screening it.

Scan a site →

Or read a sample report first