Substation Scout

Rocky Run to Werner West line substation interconnection queue

2 active projects totaling 798 MW in the MISO queue.

2 MISO queue filings name Rocky Run to Werner West line as the point of interconnection, all in Portage County, WI.

2active projects
798active MW
2total filed
Queue IDProjectkVMWResourceStatus
J2107 Not reported 345 399 Solar Active
J2185 Not reported 345 399 Solar Active

A request with terminal status left the queue as filed. That is a record of the filing, not evidence of injection capacity at this location. Confirm deliverability with MISO before relying on these figures.