Home / MISO / Substations / RITCHIE SWYD - TARLETON
RITCHIE SWYD - TARLETON substation interconnection queue
2 active projects
totaling 390.5 MW in the MISO queue, plus 3 with terminal status (shown grayed).
5 MISO queue filings name RITCHIE SWYD - TARLETON as the point of interconnection, all in AR.
2 active projects
390.5 active MW
5 total filed
Queue ID Project kV MW Resource Status
J3540
Not reported
230
400
Solar
Withdrawn
J3802
Not reported
230
300
Solar
Withdrawn
J2750
Not reported
230
197.5
Solar
Active
J3292
Not reported
230
193
Wind
Active
J3374
Not reported
230
65
Wind
Withdrawn
A request with terminal status left the queue as filed.
That is a record of the filing, not evidence of injection capacity at this location.
Confirm deliverability with MISO before relying on these figures.
Site Scanner draws on HIFLD substations and electric retail service
territories, newer substations HIFLD lacks from OpenStreetMap, EIA gas transmission pipelines, HIFLD gas facilities and gas
utility territories, USGS watershed boundaries, FEMA flood hazard layers and US Census
geocoding. Queue data is compiled from public interconnection
queue filings. Every figure carries its source and retrieval date.
A withdrawal records that a request left the queue. It says
nothing about injection capacity at that location. Verify with the relevant ISO before
relying on any figure. Queue datasets are tracked separately and are
not directly comparable: status vocabularies, fuel coding, and publication
cadence all differ.
Screening aid only. Not a system impact study. Contiguous US.