Substation Scout

REYNOLDS - BURR OAK substation interconnection queue

2 active projects totaling 328 MW in the MISO queue.

2 MISO queue filings name REYNOLDS - BURR OAK as the point of interconnection, all in White County, IN.

2active projects
328active MW
2total filed
Queue IDProjectkVMWResourceStatus
J2353 Not reported 345 190 Solar Active
J2657 Not reported 345 138 Battery Active

A request with terminal status left the queue as filed. That is a record of the filing, not evidence of injection capacity at this location. Confirm deliverability with MISO before relying on these figures.