Substation Scout

PORT CALCITE - RIGGSVILLE substation interconnection queue

1 active project totaling 251.5 MW in the MISO queue, plus 2 with terminal status (shown grayed).

3 MISO queue filings name PORT CALCITE - RIGGSVILLE as the point of interconnection, all in MI.

1active projects
251.5active MW
3total filed
Queue IDProjectkVMWResourceStatus
J2260 Not reported 138 251.5 Wind Active
J3668 Not reported 138 100 Solar Withdrawn
J3692 Not reported 138 100 Battery Withdrawn

A request with terminal status left the queue as filed. That is a record of the filing, not evidence of injection capacity at this location. Confirm deliverability with MISO before relying on these figures.