Pana Substation Bus substation interconnection queue

2 active projects totaling 350 MW in the MISO queue, plus 2 with terminal status (shown grayed).

4 MISO queue filings name Pana Substation Bus as the point of interconnection, all in Christian County, IL.

2active projects
350active MW
4total filed
Queue IDProjectkVMWResourceStatus
J848 Not reported 138 250 Wind Active
J979 Not reported 345 200 Wind Withdrawn
J980 Not reported 345 200 Wind Withdrawn
J912 Not reported 138 100 Solar Active

A request with terminal status left the queue as filed. That is a record of the filing, not evidence of injection capacity at this location. Confirm deliverability with MISO before relying on these figures.