Murphy Substation substation interconnection queue

2 active projects totaling 345.2 MW in the MISO queue, plus 1 with terminal status (shown grayed).

3 MISO queue filings name Murphy Substation as the point of interconnection, all in MI.

2active projects
345.2active MW
3total filed
Queue IDProjectkVMWResourceStatus
J1194 Not reported 138 225.2 Wind Operational
J1005 Not reported 345 200 Solar Withdrawn
J3124 Not reported 345 120 Solar Active

A request with terminal status left the queue as filed. That is a record of the filing, not evidence of injection capacity at this location. Confirm deliverability with MISO before relying on these figures.