Substation Scout

Missionary Substation substation interconnection queue

1 active project totaling 350 MW in the MISO queue, plus 2 with terminal status (shown grayed).

3 MISO queue filings name Missionary Substation as the point of interconnection, all in Jasper County, MS.

1active projects
350active MW
3total filed
Queue IDProjectkVMWResourceStatus
J1946 Not reported 230 350 Hybrid Active
J1020 Not reported 230 250 Solar Withdrawn
J3108 Not reported 161 180 Hybrid Withdrawn

A request with terminal status left the queue as filed. That is a record of the filing, not evidence of injection capacity at this location. Confirm deliverability with MISO before relying on these figures.