Substation Scout

Merom Substation substation interconnection queue

1 active project totaling 530 MW in the MISO queue, plus 2 with terminal status (shown grayed).

3 MISO queue filings name Merom Substation as the point of interconnection, all in Sullivan County, IN.

1active projects
530active MW
3total filed
Queue IDProjectkVMWResourceStatus
E0054 Merom Station n/r 530 Hybrid Active
J3318 Not reported 345 300 Hybrid Withdrawn
J2295 Not reported 345 200 Solar Withdrawn

A request with terminal status left the queue as filed. That is a record of the filing, not evidence of injection capacity at this location. Confirm deliverability with MISO before relying on these figures.

Site Scanner

Before you spend weeks on a site, spend seconds screening it.

Scan a site →

Or read a sample report first