Substation Scout

Majestic - Milan Line Tap substation interconnection queue

2 active projects totaling 190 MW in the MISO queue.

2 MISO queue filings name Majestic - Milan Line Tap as the point of interconnection, all in Washtenaw County, MI.

2active projects
190active MW
2total filed
Queue IDProjectkVMWResourceStatus
J1224 Not reported 345 170 Solar Active
J1329 Not reported 345 20 Battery Active

A request with terminal status left the queue as filed. That is a record of the filing, not evidence of injection capacity at this location. Confirm deliverability with MISO before relying on these figures.

Site Scanner

Before you spend weeks on a site, spend seconds screening it.

Scan a site →

Or read a sample report first