Substation Scout

M38 Substation substation interconnection queue

1 active project totaling 54.9 MW in the MISO queue, plus 1 with terminal status (shown grayed).

2 MISO queue filings name M38 Substation as the point of interconnection, all in Baraga County, MI.

1active projects
54.9active MW
2total filed
Queue IDProjectkVMWResourceStatus
J1138 Not reported 138 70 Wind Withdrawn
J704 Not reported 138 54.9 Gas Operational

A request with terminal status left the queue as filed. That is a record of the filing, not evidence of injection capacity at this location. Confirm deliverability with MISO before relying on these figures.

Site Scanner

Before you spend weeks on a site, spend seconds screening it.

Scan a site →

Or read a sample report first