Substation Scout

LIVINGSTON - TITTABAWASSEE substation interconnection queue

0 active projects totaling 0 MW in the MISO queue, plus 2 with terminal status (shown grayed).

2 MISO queue filings name LIVINGSTON - TITTABAWASSEE as the point of interconnection, all in MI.

0active projects
0active MW
2total filed
Queue IDProjectkVMWResourceStatus
J3437 Not reported 345 160 Hybrid Withdrawn
J3637 Not reported 345 90 Gas Withdrawn

A request with terminal status left the queue as filed. That is a record of the filing, not evidence of injection capacity at this location. Confirm deliverability with MISO before relying on these figures.