Substation Scout

Lakefield - Raun substation interconnection queue

0 active projects totaling 0 MW in the MISO queue, plus 2 with terminal status (shown grayed).

2 MISO queue filings name Lakefield - Raun as the point of interconnection, all in Cherokee County, IA.

0active projects
0active MW
2total filed
Queue IDProjectkVMWResourceStatus
R47 Not reported 345 100 Wind Withdrawn
R48 Not reported 345 100 Wind Withdrawn

A request with terminal status left the queue as filed. That is a record of the filing, not evidence of injection capacity at this location. Confirm deliverability with MISO before relying on these figures.