Killdeer Substation substation interconnection queue

0 active projects totaling 0 MW in the MISO queue, plus 3 with terminal status (shown grayed).

3 MISO queue filings name Killdeer Substation as the point of interconnection, all in IA.

0active projects
0active MW
3total filed
Queue IDProjectkVMWResourceStatus
PQ0002 Not reported 345 2,000 Other Withdrawn
J2105 Not reported 345 200 Battery Withdrawn
J3206 Not reported 345 194 Wind Withdrawn

A request with terminal status left the queue as filed. That is a record of the filing, not evidence of injection capacity at this location. Confirm deliverability with MISO before relying on these figures.