Substation Scout

interconnect at new Tap on proposed MVP Big Stone to Ellendale line substation interconnection queue

0 active projects totaling 0 MW in the MISO queue, plus 2 with terminal status (shown grayed).

2 MISO queue filings name interconnect at new Tap on proposed MVP Big Stone to Ellendale line as the point of interconnection, all in Grant County, SD.

0active projects
0active MW
2total filed
Queue IDProjectkVMWResourceStatus
J650 Not reported 345 151.8 Wind Withdrawn
J651 Not reported 345 151.8 Wind Withdrawn

A request with terminal status left the queue as filed. That is a record of the filing, not evidence of injection capacity at this location. Confirm deliverability with MISO before relying on these figures.

Site Scanner

Before you spend weeks on a site, spend seconds screening it.

Scan a site →