INDIANOLA 230/115 SUB - TILLATOBA substation interconnection queue
3 active projects totaling 570 MW in the MISO queue, plus 3 with terminal status (shown grayed).
6 MISO queue filings name INDIANOLA 230/115 SUB - TILLATOBA as the point of interconnection, all in Sunflower County, MS.
3active projects
570active MW
6total filed
| Queue ID | Project | kV | MW | Resource | Status |
|---|---|---|---|---|---|
| J3623 | Not reported | 230 | 350 | Wind | Active |
| J3774 | Not reported | 230 | 303 | Solar | Withdrawn |
| J3595 | Not reported | 230 | 230 | Solar | Withdrawn |
| J3900 | Not reported | 230 | 163 | Wind | Active |
| J3366 | Not reported | 230 | 150 | Wind | Withdrawn |
| J3592 | Not reported | 230 | 57 | Wind | Active |
A request with terminal status left the queue as filed. That is a record of the filing, not evidence of injection capacity at this location. Confirm deliverability with MISO before relying on these figures.