0 active projects
totaling 0 MW in the MISO queue, plus 3 with terminal status (shown grayed).
3 MISO queue filings name Independence ISES - Powerline Road as the point of interconnection, all in Craighead County, AR.
0active projects
0active MW
3total filed
Queue ID
Project
kV
MW
Resource
Status
J2399
Not reported
500
500
Solar
Withdrawn
J2394
Not reported
500
200
Hybrid
Withdrawn
J2398
Not reported
500
160
Hybrid
Withdrawn
A request with terminal status left the queue as filed.
That is a record of the filing, not evidence of injection capacity at this location.
Confirm deliverability with MISO before relying on these figures.
Site Scanner
Before you spend weeks on a site, spend seconds screening it.