Substation Scout

Hutsonville - Neoga substation interconnection queue

2 active projects totaling 199.5 MW in the MISO queue, plus 1 with terminal status (shown grayed).

3 MISO queue filings name Hutsonville - Neoga as the point of interconnection, all in IL.

2active projects
199.5active MW
3total filed
Queue IDProjectkVMWResourceStatus
J1744 Not reported 138 149.5 Solar Active
J2158 Not reported 138 50 Solar Withdrawn
J2159 Not reported 138 50 Battery Active

A request with terminal status left the queue as filed. That is a record of the filing, not evidence of injection capacity at this location. Confirm deliverability with MISO before relying on these figures.

Site Scanner

Before you spend weeks on a site, spend seconds screening it.

Scan a site →

Or read a sample report first