Substation Scout

Hazelton Substation substation interconnection queue

0 active projects totaling 0 MW in the MISO queue, plus 2 with terminal status (shown grayed).

2 MISO queue filings name Hazelton Substation as the point of interconnection, all in IA.

0active projects
0active MW
2total filed
Queue IDProjectkVMWResourceStatus
G589 Not reported 345 750 Coal Withdrawn
G972 Not reported 345 400 Wind Withdrawn

A request with terminal status left the queue as filed. That is a record of the filing, not evidence of injection capacity at this location. Confirm deliverability with MISO before relying on these figures.

Site Scanner

Before you spend weeks on a site, spend seconds screening it.

Scan a site →

Or read a sample report first