Substation Scout

Greentown - Walton. substation interconnection queue

2 active projects totaling 330 MW in the MISO queue, plus 1 with terminal status (shown grayed).

3 MISO queue filings name Greentown - Walton. as the point of interconnection, all in Miami County, IN.

2active projects
330active MW
3total filed
Queue IDProjectkVMWResourceStatus
J3719 Not reported 230 200 Solar Active
J2307 Not reported 230 130 Solar Active
J2308 Not reported 230 35 Battery Withdrawn

A request with terminal status left the queue as filed. That is a record of the filing, not evidence of injection capacity at this location. Confirm deliverability with MISO before relying on these figures.

Site Scanner

Before you spend weeks on a site, spend seconds screening it.

Scan a site →

Or read a sample report first