Gibson Sta to Petersburg (IP&L) substation interconnection queue
0 active projects
totaling 0 MW in the MISO queue, plus 2 with terminal status (shown grayed).
2 MISO queue filings name Gibson Sta to Petersburg (IP&L) as the point of interconnection, all in Pike County, IN.
0active projects
0active MW
2total filed
Queue ID
Project
kV
MW
Resource
Status
J2507
Not reported
345
250
Solar
Withdrawn
J2514
Not reported
345
100
Battery
Withdrawn
A request with terminal status left the queue as filed.
That is a record of the filing, not evidence of injection capacity at this location.
Confirm deliverability with MISO before relying on these figures.