Substation Scout

Emery substation interconnection queue

1 active project totaling 98 MW in the MISO queue, plus 1 with terminal status (shown grayed).

2 MISO queue filings name Emery as the point of interconnection, all in Cerro Gordo County, IA.

1active projects
98active MW
2total filed
Queue IDProjectkVMWResourceStatus
J1864 Not reported 161 250 Wind Withdrawn
J4145 Not reported n/r 98 Gas Active

A request with terminal status left the queue as filed. That is a record of the filing, not evidence of injection capacity at this location. Confirm deliverability with MISO before relying on these figures.

Site Scanner

Before you spend weeks on a site, spend seconds screening it.

Scan a site →

Or read a sample report first