Substation Scout

El Dorado Substation substation interconnection queue

2 active projects totaling 500 MW in the MISO queue, plus 2 with terminal status (shown grayed).

4 MISO queue filings name El Dorado Substation as the point of interconnection, all in Union County, AR.

2active projects
500active MW
4total filed
Queue IDProjectkVMWResourceStatus
J1872 Not reported 500 250 Solar Active
J1873 Not reported 500 250 Solar Active
J1874 Not reported 500 75 Battery Withdrawn
J1875 Not reported 500 75 Battery Withdrawn

A request with terminal status left the queue as filed. That is a record of the filing, not evidence of injection capacity at this location. Confirm deliverability with MISO before relying on these figures.