Substation Scout

El Dorado EHV - Sarepta 345/ SW STA substation interconnection queue

1 active project totaling 300 MW in the MISO queue, plus 1 with terminal status (shown grayed).

2 MISO queue filings name El Dorado EHV - Sarepta 345/ SW STA as the point of interconnection, all in Columbia County, AR.

1active projects
300active MW
2total filed
Queue IDProjectkVMWResourceStatus
J3131 Not reported 115 300 Solar Active
J3132 Not reported 115 150 Battery Withdrawn

A request with terminal status left the queue as filed. That is a record of the filing, not evidence of injection capacity at this location. Confirm deliverability with MISO before relying on these figures.

Site Scanner

Before you spend weeks on a site, spend seconds screening it.

Scan a site →

Or read a sample report first