Donaldsonville - Evergreen substation interconnection queue

1 active project totaling 175 MW in the MISO queue, plus 2 with terminal status (shown grayed).

3 MISO queue filings name Donaldsonville - Evergreen as the point of interconnection, all in Iberville Parish, LA.

1active projects
175active MW
3total filed
Queue IDProjectkVMWResourceStatus
J1668 Not reported 230 194 Solar Withdrawn
J1583 Not reported 230 175 Solar Active
J2220 Not reported 230 50 Battery Withdrawn

A request with terminal status left the queue as filed. That is a record of the filing, not evidence of injection capacity at this location. Confirm deliverability with MISO before relying on these figures.