Substation Scout

DARNELL substation interconnection queue

1 active project totaling 150 MW in the MISO queue, plus 1 with terminal status (shown grayed).

2 MISO queue filings name DARNELL as the point of interconnection, all in LA.

1active projects
150active MW
2total filed
Queue IDProjectkVMWResourceStatus
J4143 Not reported n/r 150 Solar Active
J2699 Not reported 115 58.1 Solar Withdrawn

A request with terminal status left the queue as filed. That is a record of the filing, not evidence of injection capacity at this location. Confirm deliverability with MISO before relying on these figures.

Site Scanner

Before you spend weeks on a site, spend seconds screening it.

Scan a site →

Or read a sample report first