0 active projects
totaling 0 MW in the MISO queue, plus 3 with terminal status (shown grayed).
3 MISO queue filings name Crandall Substation as the point of interconnection, all in Cottonwood County, MN.
0active projects
0active MW
3total filed
Queue ID
Project
kV
MW
Resource
Status
J1349
Not reported
345
335
Hybrid
Withdrawn
J3125
Not reported
345
289
Wind
Withdrawn
J3217
Not reported
345
60
Solar
Withdrawn
A request with terminal status left the queue as filed.
That is a record of the filing, not evidence of injection capacity at this location.
Confirm deliverability with MISO before relying on these figures.
Site Scanner
Before you spend weeks on a site, spend seconds screening it.