Cayuga - Nucor substation interconnection queue

0 active projects totaling 0 MW in the MISO queue, plus 2 with terminal status (shown grayed).

2 MISO queue filings name Cayuga - Nucor as the point of interconnection, all in IN.

0active projects
0active MW
2total filed
Queue IDProjectkVMWResourceStatus
J754 Not reported 345 303.6 Wind Withdrawn
H027 Not reported 345 200 Wind Withdrawn

A request with terminal status left the queue as filed. That is a record of the filing, not evidence of injection capacity at this location. Confirm deliverability with MISO before relying on these figures.