Cash-Newport AB line substation interconnection queue
0 active projects
totaling 0 MW in the MISO queue, plus 2 with terminal status (shown grayed).
2 MISO queue filings name Cash-Newport AB line as the point of interconnection, all in AR.
0active projects
0active MW
2total filed
Queue ID
Project
kV
MW
Resource
Status
J2356
Not reported
161
200
Hybrid
Withdrawn
J370
Not reported
161
50
Solar
Withdrawn
A request with terminal status left the queue as filed.
That is a record of the filing, not evidence of injection capacity at this location.
Confirm deliverability with MISO before relying on these figures.