Substation Scout

Burr Oak substation interconnection queue

1 active project totaling 150 MW in the MISO queue, plus 1 with terminal status (shown grayed).

2 MISO queue filings name Burr Oak as the point of interconnection, all in Marshall County, IN.

1active projects
150active MW
2total filed
Queue IDProjectkVMWResourceStatus
J1802 Not reported 138 150 Solar Active
J2418 Not reported 138 140 Battery Withdrawn

A request with terminal status left the queue as filed. That is a record of the filing, not evidence of injection capacity at this location. Confirm deliverability with MISO before relying on these figures.

Site Scanner

Before you spend weeks on a site, spend seconds screening it.

Scan a site →

Or read a sample report first