Brinkley East to Clarendon substation interconnection queue
0 active projects
totaling 0 MW in the MISO queue, plus 2 with terminal status (shown grayed).
2 MISO queue filings name Brinkley East to Clarendon as the point of interconnection, all in Monroe County, AR.
0active projects
0active MW
2total filed
Queue ID
Project
kV
MW
Resource
Status
J2141
Not reported
115
100
Solar
Withdrawn
J1789
Not reported
115
6
Solar
Withdrawn
A request with terminal status left the queue as filed.
That is a record of the filing, not evidence of injection capacity at this location.
Confirm deliverability with MISO before relying on these figures.