BOGALUSA substation interconnection queue

0 active projects totaling 0 MW in the MISO queue, plus 2 with terminal status (shown grayed).

2 MISO queue filings name BOGALUSA as the point of interconnection, all in Washington Parish, LA.

0active projects
0active MW
2total filed
Queue IDProjectkVMWResourceStatus
J2743 Not reported n/r 175 Solar Withdrawn
J1906 Not reported n/r 100 Battery Withdrawn

A request with terminal status left the queue as filed. That is a record of the filing, not evidence of injection capacity at this location. Confirm deliverability with MISO before relying on these figures.

Site Scanner

Before you spend weeks on a site, spend seconds screening it.

Scan a site →

Or read a sample report first