Home / MISO / Substations / Blue Lake
Blue Lake substation interconnection queue
3 active projects
totaling 575.5 MW in the MISO queue.
3 MISO queue filings name Blue Lake as the point of interconnection, all in Scott County, MN.
3 active projects
575.5 active MW
3 total filed
Queue ID Project kV MW Resource Status
G369
Not reported
115
385
Gas
Operational
R1050
Replacing 135.5 MW with 135.5 MW BESS; Blue Lake Units 1 2 4
115
135.5
Hybrid
Active
R1051
Replacing 55 MW with 29 MW Natural Gas/Fuel Oil; Blue Lake Unit 3
115
55
Hybrid
Active
A request with terminal status left the queue as filed.
That is a record of the filing, not evidence of injection capacity at this location.
Confirm deliverability with MISO before relying on these figures.
Site Scanner draws on HIFLD substations and electric retail service
territories, newer substations HIFLD lacks from OpenStreetMap, EIA gas transmission pipelines, HIFLD gas facilities and gas
utility territories, USGS watershed boundaries, FEMA flood hazard layers and US Census
geocoding. Queue data is compiled from public interconnection
queue filings. Every figure carries its source and retrieval date.
A withdrawal records that a request left the queue. It says
nothing about injection capacity at that location. Verify with the relevant ISO before
relying on any figure. Queue datasets are tracked separately and are
not directly comparable: status vocabularies, fuel coding, and publication
cadence all differ.
Screening aid only. Not a system impact study. Contiguous US.