0 active projects
totaling 0 MW in the MISO queue, plus 5 with terminal status (shown grayed).
5 MISO queue filings name Bison Substation as the point of interconnection, all in Cass County, ND.
0active projects
0active MW
5total filed
Queue ID
Project
kV
MW
Resource
Status
J1613
Not reported
345
400
Wind
Withdrawn
J1109
Not reported
345
207
Wind
Withdrawn
J1170
Not reported
345
200
Solar
Withdrawn
J743
Not reported
345
200
Wind
Withdrawn
J946
Not reported
345
200
Solar
Withdrawn
A request with terminal status left the queue as filed.
That is a record of the filing, not evidence of injection capacity at this location.
Confirm deliverability with MISO before relying on these figures.
Site Scanner