Substation Scout

BAXTER WILSON SES SWYD - PERRYVILLE 500 SWYD substation interconnection queue

1 active project totaling 300 MW in the MISO queue, plus 4 with terminal status (shown grayed).

5 MISO queue filings name BAXTER WILSON SES SWYD - PERRYVILLE 500 SWYD as the point of interconnection, all in LA.

1active projects
300active MW
5total filed
Queue IDProjectkVMWResourceStatus
J4141 Not reported 500 650 Gas Withdrawn
J3273 Not reported 500 473.8 Wind Withdrawn
J3760 Not reported 500 405 Solar Withdrawn
J3454 Not reported 500 300 Solar Active
J3452 Not reported 500 50 Battery Withdrawn

A request with terminal status left the queue as filed. That is a record of the filing, not evidence of injection capacity at this location. Confirm deliverability with MISO before relying on these figures.