0 active projects totaling 0 MW in the MISO queue, plus 2 with terminal status (shown grayed).

2 MISO queue filings name Babcock - Lake George as the point of interconnection, all in Porter County, IN.

0active projects
0active MW
2total filed
Queue IDProjectkVMWResourceStatus
J1742 Not reported 345 294.1 Solar Withdrawn
J1683 Not reported 345 75 Battery Withdrawn

A request with terminal status left the queue as filed. That is a record of the filing, not evidence of injection capacity at this location. Confirm deliverability with MISO before relying on these figures.