Anson station substation interconnection queue

0 active projects totaling 0 MW in the MISO queue, plus 2 with terminal status (shown grayed).

2 MISO queue filings name Anson station as the point of interconnection, all in Minnehaha County, SD.

0active projects
0active MW
2total filed
Queue IDProjectkVMWResourceStatus
G764 Not reported 115 241.5 Wind Withdrawn
G763 Not reported 115 50 Wind Withdrawn

A request with terminal status left the queue as filed. That is a record of the filing, not evidence of injection capacity at this location. Confirm deliverability with MISO before relying on these figures.