ALEXANDRIA substation interconnection queue

1 active project totaling 39.5 MW in the MISO queue, plus 1 with terminal status (shown grayed).

1active projects
39.5active MW
2total filed
Queue IDProjectkVMWResourceStatus
J2605 Not reported 345 339 Wind Withdrawn
J2276 Not reported n/r 39.5 Hybrid Active

A request with terminal status left the queue as filed. That is a record of the filing, not evidence of injection capacity at this location. Confirm deliverability with MISO before relying on these figures.