Substation Scout

7PR STATE - 7MTVERNW substation interconnection queue

0 active projects totaling 0 MW in the MISO queue, plus 2 with terminal status (shown grayed).

2 MISO queue filings name 7PR STATE - 7MTVERNW as the point of interconnection, all in IL.

0active projects
0active MW
2total filed
Queue IDProjectkVMWResourceStatus
J3878 Not reported 345 300 Solar Withdrawn
J3410 Not reported 345 120 Solar Withdrawn

A request with terminal status left the queue as filed. That is a record of the filing, not evidence of injection capacity at this location. Confirm deliverability with MISO before relying on these figures.

Site Scanner

Before you spend weeks on a site, spend seconds screening it.

Scan a site →

Or read a sample report first