Substation Scout

Surplus; J385

MISO queue ID S1110

Surplus; J385 (S1110) was listed in the MISO interconnection queue at the end of 2025 as a 100 MW battery project in Chisago County, MN, according to Berkeley Lab’s queue data file. The filing names CHISAGO COUNTY as its point of interconnection. Its status as of December 31, 2025 was “Active”, with a proposed online date of October 1, 2027.

Queue IDS1110
Project nameSurplus; J385
Status (as published)Active
SubstationCHISAGO COUNTY
Point of interconnectionCHISAGO COUNTY
CountyChisago
StateMN
VoltageNot reported
Capacity100 MW
Resource (as published)Battery
Resource categoryBattery (normalized for filtering)
Proposed online date2027-10-01
Source datasetBerkeley Lab Queued Up: 2026 Edition (Lawrence Berkeley National Laboratory and GridTracker, CC BY 4.0), requests through December 31, 2025

Same substation and county

CHISAGO COUNTY substation: 2 requests in the MISO queue, 1 active totaling 100 MW.

Queue IDProjectMWResourceStatus
J3500Not reported150BatteryWithdrawn

Chisago, MN: 16 requests in the MISO queue, 5 active totaling 650 MW.

Tracked changes

Not tracked. MISO rows come from an annual snapshot (requests through December 31, 2025), so this site does not compare them week to week.

Additional filed fields

UtilityNORTHERN STATES POWER COMPANY
Project typeGeneration
Queue date2025-08-22

Capacity is the first resource type’s MW as the data file gives it; a hybrid’s other components are listed under Components and are not added in.

Fields shown are those in Berkeley Lab’s data file, which standardizes each provider’s queue. The provider’s own queue may carry more fields and newer values. Always confirm against it before relying on any value.