Substation Scout

Surplus; J1188

MISO queue ID S1025

Surplus; J1188 (S1025) was listed in the MISO interconnection queue at the end of 2025 as a 25 MW hybrid project in Rock County, WI, according to Berkeley Lab’s queue data file. The filing names Sheepskin as its point of interconnection. Its status as of December 31, 2025 was “Active”, with a proposed online date of June 1, 2022.

Queue IDS1025
Project nameSurplus; J1188
Status (as published)Active
SubstationSheepskin
Point of interconnectionSheepskin 69kV
CountyRock
StateWI
Voltage69 kV
Capacity25 MW
Resource (as published)Other+Battery
Resource categoryHybrid (normalized for filtering)
Proposed online date2022-06-01
Source datasetBerkeley Lab Queued Up: 2026 Edition (Lawrence Berkeley National Laboratory and GridTracker, CC BY 4.0), requests through December 31, 2025

Same substation and county

Rock, WI: 26 requests in the MISO queue, 15 active totaling 2,594.1 MW.

Tracked changes

Not tracked. MISO rows come from an annual snapshot (requests through December 31, 2025), so this site does not compare them week to week.

Additional filed fields

UtilityAMERICAN TRANSMISSION COMPANY
Project typeGeneration
Queue date2022-05-16
Components (hybrid)Other 25 MW + Battery

Capacity is the first resource type’s MW as the data file gives it; a hybrid’s other components are listed under Components and are not added in.

Fields shown are those in Berkeley Lab’s data file, which standardizes each provider’s queue. The provider’s own queue may carry more fields and newer values. Always confirm against it before relying on any value.