Substation Scout

Surplus; J893 (Searcy Solar)

MISO queue ID S1000

Surplus; J893 (Searcy Solar) (S1000) was listed in the MISO interconnection queue at the end of 2025 as a 10 MW hybrid project, according to Berkeley Lab’s queue data file. The filing names Searcy Price Sub as its point of interconnection. Its status as of December 31, 2025 was “Active”.

Queue IDS1000
Project nameSurplus; J893 (Searcy Solar)
Status (as published)Active
SubstationSearcy Price Sub
Point of interconnectionSearcy Price Sub 161kV
CountyNot reported
StateNot reported
Voltage161 kV
Capacity10 MW
Resource (as published)Other+Battery
Resource categoryHybrid (normalized for filtering)
Proposed online dateNot reported
Source datasetBerkeley Lab Queued Up: 2026 Edition (Lawrence Berkeley National Laboratory and GridTracker, CC BY 4.0), requests through December 31, 2025

Same substation and county

Searcy Price Sub substation: 2 requests in the MISO queue, 2 active totaling 110 MW.

Queue IDProjectMWResourceStatus
J893Not reported100SolarOperational

Tracked changes

Not tracked. MISO rows come from an annual snapshot (requests through December 31, 2025), so this site does not compare them week to week.

Additional filed fields

UtilityEntergy
Interconnection serviceNRIS
Project typeGeneration
Queue date2020-06-20
Operational date2022-01-21
Components (hybrid)Other 10 MW + Battery

Capacity is the first resource type’s MW as the data file gives it; a hybrid’s other components are listed under Components and are not added in.

Fields shown are those in Berkeley Lab’s data file, which standardizes each provider’s queue. The provider’s own queue may carry more fields and newer values. Always confirm against it before relying on any value.

Site Scanner

Before you spend weeks on a site, spend seconds screening it.

Scan a site →

Or read a sample report first