Replacing 124.4 MW of existing gas generation with solar at Woodruff County (formerly Bailey); Woodruff Co Solar
MISO queue ID R1016
Replacing 124.4 MW of existing gas generation with solar at Woodruff County (formerly Bailey); Woodruff Co Solar (R1016) was listed in the MISO interconnection queue at the end of 2025 as a 124.4 MW hybrid project, according to Berkeley Lab’s queue data file. The filing names Bailey substation as its point of interconnection. Its status as of December 31, 2025 was “Active”, with a proposed online date of May 10, 2023.
| Queue ID | R1016 |
|---|---|
| Project name | Replacing 124.4 MW of existing gas generation with solar at Woodruff County (formerly Bailey); Woodruff Co Solar |
| Status (as published) | Active |
| Substation | Bailey substation |
| Point of interconnection | Bailey 161kV substation(338879) |
| County | Not reported |
| State | Not reported |
| Voltage | 161 kV |
| Capacity | 124.4 MW |
| Resource (as published) | Solar+Other |
| Resource category | Hybrid (normalized for filtering) |
| Proposed online date | 2023-05-10 |
| Source dataset | Berkeley Lab Queued Up: 2026 Edition (Lawrence Berkeley National Laboratory and GridTracker, CC BY 4.0), requests through December 31, 2025 |
Tracked changes
Not tracked. MISO rows come from an annual snapshot (requests through December 31, 2025), so this site does not compare them week to week.
Additional filed fields
| Utility | ENTERGY ARKANSAS INC. |
|---|---|
| Interconnection service | NRIS |
| Project type | Generation |
| Queue date | 2022-02-18 |
| Operational date | 2024-10-04 |
| Components (hybrid) | Solar 124.4 MW + Other |
Capacity is the first resource type’s MW as the data file gives it; a hybrid’s other components are listed under Components and are not added in.
Fields shown are those in Berkeley Lab’s data file, which standardizes each provider’s queue. The provider’s own queue may carry more fields and newer values. Always confirm against it before relying on any value.